NASA and Blue Origin announced Friday that they have agreed to delay the launch of the ESCAPADE mission to Mars until at least the spring of 2025.
The decision to stand down from a launch attempt in mid-October was driven by a deadline to begin loading hypergolic propellant on the two small ESCAPADE (Escape and Plasma Acceleration and Dynamics Explorers) spacecraft. While it is theoretically possible to offload fuel from these vehicles for a future launch attempt, multiple sources told Ars that such an activity would incur significant risk to the spacecraft.
Forced to make a call on whether to fuel, NASA decided not to. Although the two spacecraft were otherwise ready for launch, it was not clear the New Glenn rocket would be similarly ready to go.
Waiting on the rocket
NASA procured the debut launch of the New Glenn rocket, which was developed by Blue Origin, for a significant discount. The mission’s managers, University of California, Berkeley’s Space Sciences Laboratory, always understood there were timeline risks with launching on New Glenn.
Blue Origin appears to have worked with some urgency this year to prepare the massive rocket for its initial launch. However, when the company missed a key target of hot firing the rocket’s upper stage by the end of August, NASA delayed fueling of the ESCAPADE mission. Now, with the closing of a Mars launch window next month, NASA will not fuel the spacecraft until next spring, at the earliest.
Founded by Amazon’s Jeff Bezos, Blue Origin successfully rolled the New Glenn second stage to its launch pad at Launch Complex-36 in Florida on Tuesday. The company is now targeting Monday, September 9, for a hot fire test of the second stage.